桃源水电站船闸下游引航道主导航墙结构型式研究 被引量:2

Study on Structure Type of Downstream Main Approach Channel Wall of Ship Lock in Taoyuan Hydropower Station
下载PDF
导出
摘要 桃源水电站船闸下游引航道主导航墙有450 m位于一期围堰之外,如另做子围堰旱地施工,工期难以保证且投资较高。为解决上述问题,充分利用引航道的地形、地质条件,对下游引航道主导航墙结构型式进行了多方案比选,最终采用"混凝土桩+高喷基础"方案,达到了取消子围堰施工、节省工期、节约投资之目的。 The downstream main approach channel wall of ship lock in Taoyuan Hydropower Station has a section of 450m-long located outside the Phase I cotterdam. It is difficult to meet the requirements on construction period and investment if this section approach channel wall is constructed on a dry condition by building a sub-cofferdam. For solving these problems, different structure types of main approach channel wall are compared, and the combination of concrete piles and high-pressure jet grouting foundation are finally determined to be used after considering the topographic and geologic conditions of approach channel.
出处 《水力发电》 北大核心 2014年第6期39-41,共3页 Water Power
关键词 导航墙结构型式 船闸 方案比选 桃源水电站 structure type of approach channel wall ship lock scheme comparison Taoyuan Hydropower Station
  • 相关文献

参考文献5

二级参考文献9

  • 1JTJ306-2001,船闸输水系统设计规范[S].北京:人民交通出版社,2001.
  • 2《船闸水工建筑物设计规范》.JTJ307-20011.
  • 3JTJ307—2001船闸水工建筑物设计规范[S].北京:人民交通出版社,2001.
  • 4JTJ305-2001.船闸总体设计规范[S].[S].,..
  • 5JTJ307-2001.船闸水工建筑物设计规范[S].[S].,..
  • 6JTJ291-1998,高桩码头设计与施工规范[S].
  • 7JTJ 267-1998,港口工程混凝土结构设计规范[S].
  • 8江苏省水利勘测设计研究院.宝应船闸扩容改造工程施工图设计项目竞聘文件[R].扬州:江苏省水利勘测设计研究院,2009.
  • 9江苏省水利勘测设计研究院.宝应船闸扩容改造工程施工图设计[R].扬州:江苏省水利勘测设计研究院,2009.

共引文献6

同被引文献21

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部