摘要
涪陵地区页岩气井井深较深、水平段长、施工压力高,对连续油管作业设备、材料的配置要求高。但受施工条件及道路通行条件限制,不能过高配置施工设备。在保证施工质量、确保施工安全的前提下,以够用为原则,合理配置涪陵页岩气产建区连续油管作业设备、材料较为适宜。
Due to its deeper hole, long horizontal segment and high pressure in operation, shale gas well in Fuling area asks for higher configuration of coiled tubing unit and stuff. However, limited by conditions of operation and road, operation equipments are unable to use too high configuration. Therefore, it is proper to configure them appropriately on the premise of ensuring operation quality and operation safety.
出处
《江汉石油职工大学学报》
2014年第3期50-52,共3页
Journal of Jianghan Petroleum University of Staff and Workers
关键词
涪陵地区
页岩气
连续油管
设备
优化配置
Fuling Area
Shale Gas
Coiled Tubing
Equipment
Optimal Configuration