新建线施工及运营对下部既有线影响研究

Study on the impact of new tunnel line construction and operation upon lower existing-tunnel line
下载PDF
导出
摘要 基于深圳彩田路新彩隧道北口段(拟建)近距离上跨厦深铁路梅林隧道两条隧道叠置的工程实例,运用有限元分析软件MIDAS-GTS进行三维模型数值分析,研究了新建隧道拟用施工方案及加固方案的可行性,分析了新建隧道在施工及运营阶段,既有隧道的变形及内力变化规律,并对既有隧道的安全性进行了评价,结果表明:选用的施工方法在新建新彩隧道施工及运营阶段不会影响既有线路的运营安全性。 Based on two tunnel overlapping engineering example of Xincai tunnel north section on Caitian road in Shenzhen over-crossing Meilin tunnel of Xia-Shen railway, the paper applies finite element analysis software MIDAS-GTS and carries out three-dimensional numerical simulation, studies the feasibilities of new tunnel construction scheme and reinforcement scheme, analyzes existing tunnel deformation and its internal force alteration law at new tunnel construction and operation phases, and estimates existing tunnel security. Results show that: the selected construction method will not influence existing tunnel line operation safety at Xincai tunnel construction and operation phases.
出处 《山西建筑》 2014年第18期183-184,共2页 Shanxi Architecture
关键词 隧道工程 交叠隧道 数值模拟 明挖暗埋法 tunnel engineering overlap tunnel numerical simulation open-excavation and hidden-burying method
  • 相关文献

参考文献6

二级参考文献55

共引文献259

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部