摘要
天津滨海旅游区起步区雨水泵站设计规模为8.0 m3/s。此设计在排水规划基础上紧密结合现场实际情况,对原有泵站进行改造。经方案比选后,采用双向顶管法实施泵站出水管道施工。在保证泵站基本工艺及功能的前提下,达到保护环境、节省投资的目的。
Located in Tianjin Binhai Tourism Starting Zone, the designed scale of rainwater pumping station is 8.0 m3/s. This design is to reform the existed rainwater pumping station with the consideration of the drainage planning and the current site conditions. With the comparison to different treatment plans, the two-way pipejacking method is chosen to be the optimal design for output water pipelines. This method can arrive at protecting environment and saving cost on the premise of ensuring basic technology and function of the pump station.
出处
《中国市政工程》
2014年第3期43-45,103-104,共3页
China Municipal Engineering
关键词
雨水泵站
改造
出水管道
顶管施工
水泵
rainwater pumping station
reform
output water pipelines
pipe-jacking construction
water pump