隧洞塌方引起的TBM刀盘被卡事故风险评估 被引量:4

Risk Assessment on the Accident of TBM Cutterhead Jamming Caused by Tunnel Collapse
下载PDF
导出
摘要 隧道掘进机(TBM)在节理岩体中掘进,刀盘可能被困;为了减少损失,进行风险评估很有必要。通过刀盘被困理论分析可知,刀盘被卡与否取决于扭矩与阻力矩的关系;阻力矩大小由塌方高度决定,根据塌方高度的随机特性,结合概率理论建立了刀盘被卡概率计算公式。同时,根据塌方产生的阻力矩的大小和TBM刀盘参数,将刀盘被困的后果分为5个等级,并结合概率等级提出了刀盘的风险评价矩阵。通过工程实例计算,验证了研究结果的合理性。 The cutterhead of tunnel boring machine( TBM) working in jointed rock mass is likely to be jammed. In order to reduce the loss,risk assessment is necessary. Whether the cutterhead is jammed or not depends on the relationship between torque and resistance torque. The magnitude of resistance torque depends on the height of collapse. According to the randomicity of collapse height and the theory of probability,a formula for calculating the probability of cutterhead jamming is established. Meanwhile,according to the magnitude of resistance torque and cutterhead's parameters,the consequences of cutterhead jamming is divided into five ranks. On the basis of probability and consequence ranks,risk assessment matrix for TBM cutterhead is proposed. The research results are verified reasonable by practical example.
作者 温森 孔庆梅
出处 《长江科学院院报》 CSCD 北大核心 2014年第4期59-62,共4页 Journal of Changjiang River Scientific Research Institute
基金 国家自然科学基金资助项目(50709008) 河南省教育厅科学技术研究重点项目(13A560081)
关键词 隧洞塌方 风险评估 TBM刀盘 阻力矩 风险评价矩阵 tunnel collapse risk assessment TBM cutterhead resistance torque risk assessment matrix
  • 相关文献

参考文献9

二级参考文献24

  • 1宋天田,肖正学,苏华友,卢小霞.上公山TBM施工2·22卡机事故工程地质分析[J].岩石力学与工程学报,2004,23(z1):4544-4546. 被引量:29
  • 2宋克志,王梦恕.隧道地层变位的可靠性分析[J].中国安全科学学报,2004,14(6):82-86. 被引量:5
  • 3苏华友,张继春,史丽华.TBM通过不良地质地段的施工技术[J].岩石力学与工程学报,2005,24(9):1635-1638. 被引量:25
  • 4尚彦军,史永跃,曾庆利,尹俊涛,薛继洪.昆明上公山隧道复杂地质条件下TBM卡机及护盾变形问题分析和对策[J].岩石力学与工程学报,2005,24(21):3858-3863. 被引量:83
  • 5张镜剑 李典璜 薛继洪 王思敬 杨志法 傅冰骏.长大隧道掘进机的应用及其主要岩石力学问题的处理[A].王思敬,杨志法,傅冰骏.中国岩石力学与工程世纪成就[M].南京:河海大学出版社,2004.582-597.
  • 6国家电力公司昆明勘测设计研究院.掌鸠河引水供水工程土建I标招标文件[R].昆明:掌鸠河引水供水工程建设管理局,2002..
  • 7Yassaghi A, Salari-Rad H. Squeezing rock conditions at an igneous contact zone in the Taloun tunnels, Tehran-Shomal freeway, Iran: a case study[J]. International Journal of Rock Mechanics and Mining Sciences, 2005, 42: 95 - 108.
  • 8Egger P. Design and construction aspect of deep tunnels(with particular emphasis on strain softening rocks)[J]. Tunnelling and Underground Space Technology, 2000, 15(4): 403 - 408.
  • 9Shalabi F I. FE analysis of time-dependent behavior of tunneling in squeezing ground using two different creep models[J]. Tunnelling and Underground Space Technology, 2005, 20(2): 271 - 279.
  • 10Goel R K, Jethwa J L, Pathankar A G. Indian experience with Q and RMR system[J]. Tunnelling and Underground Space Technology,1995, 10(1): 97- 109.

共引文献177

同被引文献33

引证文献4

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部