摘要
针对制丝、卷接包生产线配备的变压器负载系数普遍偏低的情况,从设计、运行全过程进行分析,考察了变压器实际运行工况,查找主因。提出了加强数据采集准确性管理、补充完善设计手册需要系数和同时系数、灵活调度变压器运行来提高负载系数的应对措施。
The cut tobacco production line, the cigarette package transformer production line with the load coefficient is the lower, running from the whole process of design, analysis, the actual operation of transformer condition, find the main reason. Put forward to strengthen management, improve the accuracy of data acquisition design manual Demand coefficient and synchronous coefficient, flexible scheduling of transformer operation to improve measures load coefficient.
出处
《电气技术》
2014年第1期78-80,共3页
Electrical Engineering