某高层建筑地下室严重渗漏 ,经调查、分析 ,是由于勘察、设计及施工单位一系列失误 ,导致筏基底板砼产生变形裂缝及砼内部存在渗水通路引起渗漏。经采用“堵、导”结合的办法 ,有效地防治了渗漏 。
Water leakage occurred seriously in the basement of a high building After investigation and analysis,we found out the fact that the concrete of bottom plate at the raft foundation was out of shape and therefore formed crevices, and there was a water leaking passage in the interior of concrete And the unit of reconnaissance,designing and construction should be responsible for the above situations We have prevented water leakage effectively and ensured the normal usage of the basement by the way of stoppage and leading