摘要 北京地铁6号线平安里站—北海北站区间采用矿山暗挖法下穿既有地铁4号线,为保证既有4号线运营安全,应用远程自动化监测系统对既有4号线的隧道结构及线路进行实时监测,通过施工期间的实时监测,快速反馈信息,指导施工,保障了新建6号线的顺利下穿和既有4号线的运营安全。 When Beijing metro line 6 under-passed existing metro line 4 in the section of Ping'anli station Beihai North station by using mine tunneling method, in order to ensure tile safe operations of metro line 4, real-time monitoring is carried out on existing Line 4 line tunnel structure and track by using remote automatic monitoring system. By real-time monitoring during construction, rapid feedback guides the construction to ensure of smooth under-passing of existing line 4 and safe operation of new line 6.
作者 冯振鲁
出处 《现代城市轨道交通》 2014年第3期65-67,79,共4页 Modern Urban Transit
关键词 地铁 下穿既有隧道 运营线路 远程监测 metro under-passing existing tunnel commercial line remote monitoring
  • 相关文献

参考文献6

  • 1北京城建设计总院有限责任公司.北京地铁6号线一期工程施工设计平安里站-北海北站区间竖井结构施工图[G].北京:北京城建设计总院有限责任公司,2009.
  • 2北京城建设计研究总院有限责任公司.北京地铁6号线一期工程平安里站一北海北站区间第三方监测方案设计[G].北京:北京城建设计研究总院有限责任公司,2009.
  • 3DB11/490-2007地铁工程监控量测技术规程[S].2007.
  • 4王百发,牛卓立,郭渭明等.GB 50026-2007,工程测量规范[S].北京:中华人民共和国建设部/中华人民共和国国家质量监督检验检疫总局,2007:58.
  • 5GB/T50438-2007,地铁运营安全评价标准[S ] .2007.
  • 6QB[J]BDY(A)XL003-2009北京地铁工务维修规则[G].2009.