摘要
徐葛大桥主桥为(75+95)m半飘浮体系独塔双跨预应力混凝土斜拉桥。简要介绍徐葛大桥桥型布置、最小弯曲能量法、主桥结构计算、主梁配束及施工方案。
The main bridge of Xuge Bridge is a(75+95)m semi-floating single-pylon double-span pre-stressed concrete cable-stayed bridge. The article introduces the bridge layout, the minimum bending energy method, the main bridge structural calculation, the main beam tendon layout and the construction scheme of Xuge Bridge.
出处
《城市道桥与防洪》
2014年第6期110-112,12,共3页
Urban Roads Bridges & Flood Control
关键词
斜拉桥
主梁配束
最小弯曲能量法
内力分析
施工方式
cable-stayed bridge,tendon layout of main beam,the minimum bending energy method,inner force analysis,construction method