不同排水板间距处理新吹填淤泥效果分析 被引量:6

The Effect Analysis of Newly Dredged Sludge Treatment with Different Drainage Board Spacing
下载PDF
导出
摘要 采用浅表层技术对新吹填淤泥进行地基处理时,不同排水板间距对地基处理的效果必然不同。根据排水板间距的不同设置试验区,对试验区真空预压过程中的真空度、沉降、孔压进行监测。卸载时进行了钻孔取样和平板荷载试验,并计算了其固结度。 The effectiveness of foundation treatment with different drainage board spacing would be inevitably various, when reinforcement technology of the superficial surface layer was adopted to treat foundation with newly dredged sludge. The test area was set up according to the different drainage board spacing. The vacuum, settlement and pore pressure were monitored during vacuum preloading for the test area. The method of core boring and slab loading test were carried out, and the degree of consolidation was also calculated at the time of unloading.
出处 《施工技术》 CAS 北大核心 2014年第11期119-121,126,共4页 Construction Technology
关键词 地基 软基 吹填淤泥 加固 真空预压 foundations soft foundations dredger sludge reinforcement vacuum preloading
  • 相关文献

参考文献3

二级参考文献3

  • 1JTJ240-1997港口工程地质勘查规范[S].
  • 2Bieniawski Z T. Determining rock mass deformability:experience from case histories[J]. International Journalof Rock Mechanics and Mining Sciences &Geomechanics Abstract, 1978, 15: 237-47.
  • 3Bieniawski Z T. Engineering Rock Mass Classification[M].New York: John Wiley and Sons. 1989, 1-251.

共引文献31

同被引文献47

引证文献6

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部