重复组装式导流桩坝施工消耗量研究 被引量:1

Study on Construction Quota Standard of Reusable Non-Emergency Ground Sills Groin
下载PDF
导出
摘要 分析了重复组装式导流桩坝在欧坦抢险施工过程中的水文、气象和现场地质条件,结合施工过程中对人员、材料、机械使用数量和工作过程的观测,定量分析了重复组装式导流桩坝施工定额中人员、材料、机械的消耗量。结果表明:重复组装式导流桩的费用为12.8万元/100 m,在单桩长20 m的情况下,每100延米的桩坝投资约为320万元;与传统的土石结构抢险坝相比,重复组装式导流桩坝在施工的抗干扰性、工程投资、日后的管理维护等方面均表现出一定的优势,具备推广应用的前提条件。 This paper analyzed the hydrolofical,meteorolofical and the spot feolofical conditions durinf the process of Outan emerfency repair and based on the observation of the number or amount of personnel,materials and machinery and the work process,made a quantitative analysis of the consumption of personnel,materials and machinery in the construction quota of the re-assembled diversion pile froin. The results show that the cost of the re-assembled pile dam is 128,000 Yuan/100 m,and in the case of sinfle pile lenfth of 20 m,the investment for every 100 extended meters of pile dam will be around 3. 2 million Yuan. Compared with the traditional earth-rock dam emerfency repair,the re-assembled diversion pile dam has showed some advantafes in terms of construction anti-interference,proJect investment and future maintenance,therefore,it has a precondition for popularization and application.
作者 马乐 张波
出处 《人民黄河》 CAS 北大核心 2014年第6期23-25,共3页 Yellow River
基金 水利部公益性行业科研专项(200701047 201201074)
关键词 施工定额 组装式桩坝 导流桩坝 黄河下游 construction quota assemblinf pile dike diversion pile dike Lower Yellow River
  • 相关文献

参考文献2

二级参考文献3

  • 1河南黄河勘测设计研究院.黄河下游移动式不抢险潜桩坝试验工程设计[R].2009,5.
  • 2郑州黄河水电工程有限公司.黄河下游移动式不抢险潜坝施工技术研究[R].2009,7.
  • 3JGJ 94-2008,建筑桩基技术规范[S].

共引文献10

同被引文献9

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部