摘要
本文介绍了凉山州长海子风电场工程水土流失预测范围与时段、内容与方法。通过采用类比工程法进行预测,得到了水土流失预测结果,确定了风电场水土流失重点区域为交通设施区、弃渣场区,水土流失主要时段为施工期。据此预测结果,为工程在建设过程中提出了水土保持设计建议。
This paper introduced the range and periods,contents and methods of the prediction about water and soil loss in wind power field.By using the engineering analogy method,the obtained prediction results of water and soil loss showed that the most serious area were traffic facility region and waste slag region,and the main period of water and soil loss was during the construction period.On the basis of prediction results,this paper proposed design suggestions about of water and soil loss in the construction process of the project.
出处
《四川环境》
2014年第3期113-119,共7页
Sichuan Environment
关键词
风电场
水土流失
水土流失预测
侵蚀模数
Wind power field
soil and water loss
water and soil loss prediction
erosion modulus