某火电厂水源地勘测进行稳定流抽水试验 ,通过回水达到 3个降程的规范要求 ,并在最后一个降程结束测恢复水位 ,结果水跃值反常、参数失真 ,在此基础上商讨修正及改进的方法。
In pumping test for steady flow in the water source of certain power plant three drawdowns according to the requirements of specifications have been reached through returning water.At the end of the final drawdown the recovery water level is measured.The outcomes are that the value of hydraulic jump is abnormal,the parameters become untrue.Revision and improvement are discussed based on them.
出处
《工程勘察》
CSCD
北大核心
2001年第2期29-31,共3页
Geotechnical Investigation & Surveying
关键词
稳定流抽水试验
回水
水跃值
水源
水位恢复法
pumping test for steady flow
returning water
value of hydraulic jump
recovery water levelx