期刊文献+

大直径全深冻结立井机械化配套快速施工 被引量:4

Mechanized Matched Rapid Construction of Large Diameter Mine Full Depth Freezing Shaft
下载PDF
导出
摘要 高家堡煤矿副立井净直径8.5m,采用全深冻结法凿井,冻结深度850m,凿井深度841.5m,双层钢筋混凝土井壁。井筒采用Ⅵ型凿井井架、大提升机、大吊桶、大模板、液压伞形钻架、中心回转式液压抓岩机、座钩式自动翻矸装置、自卸汽车等先进设备组成的立井快速施工机械化作业线,中深孔爆破、小型挖掘机清底、大直径输料管输送混凝土等先进技术,短段掘砌,混合作业,取得了连续5个月掘砌外壁月成井超百米,平均月成井120m的好成绩,为全深冻结立井安全快速施工提供了经验。 A net diameter of a mine auxiliary shaft in Gaojiabu Mine was 8.5m.The mine auxiliary shaft was sunk with a full depth freezing method ,the freezing depth of the auxiliary shaft was 850m ,the sinking depth of the mine shaft was 841.5m and the mine shaft liner was a double reinforced concrete shaft liner.A mechanized operation line of the mine shaft rapid construction was consisted with a Ⅵtype shaft sinking headframe ,large hoist ,large kibbles ,large formworks ,hydraulic umbrella drilling rig ,central rotating type hydraulic grabs ,bottom hook type automatic refuse tipping device ,dump trucks and other advanced equipments.A short sectional excavation and lining combined operation was applied to the mine shaft sinking with medium and deep borehole blasting ,floor cleaning with small type excavator ,concrete transportation with large diameter material transportation pipeline and other advanced technology.A month shaft completed within a continuous five month of shaft excavation and outer shaft lining was over 100m obtained ,an average month shaft completed was 120m and the expe-riences would be provided to the safety and rapid construction of the mine full depth freezing shaft.
出处 《建井技术》 2014年第2期21-26,共6页 Mine Construction Technology
关键词 立井 全深冻结 机械化配套 快速施工 Ⅵ型凿井井架 mine shaft full depth freezing mechanized matched rapid construction Ⅵ type mine shaft sinking headframe
  • 相关文献

参考文献4

二级参考文献3

共引文献9

同被引文献26

引证文献4

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部