期刊文献+

铜灌口水库坝基覆盖层的研究及利用 被引量:1

Study and Application of Tongguankou Reservoir Dam Foundation Covering Layer
下载PDF
导出
摘要 铜灌口水库工程建设中,为了减少坝基开挖,降低施工强度,节省工程投资,并保护工程区环境,通过对坝基覆盖层进行勘探、试验,结合坝体结构设计,采用三维有限单元法,研究了河床覆盖层不同的开挖方案时坝体、面板和接缝系统的应力变形特性,最终确定了坝基覆盖层合理利用的设计方案。 Based on dam structure design, stress deformation features of dam, panel and joint system of excavation programs for different riverbed covering layers are studied through exploring and testing dam foundation covering layer, and adopting three-dimensional finite element method in Tongguankou reservoir project construction in order to reduce dam foundation excavation, decrease construction intensity, save project investment, and protect environment of project area. Design program of rationally utilizing dam foundation covering layer is finally determined.
出处 《水利建设与管理》 2014年第6期23-27,共5页 Water Conservancy Construction and Management
关键词 面板堆石坝 覆盖层结构 研究 利用 综合效益 panel rock-fill dam covering layer structure study utilization comprehensive benefits
  • 相关文献

参考文献3

  • 1SL228--2013混凝土面板堆石坝设计规范[S].
  • 2南京水利科学研究院.习水县铜灌口水库工程大坝基础砂砾石层利用研究分析报告[R].2013,8.
  • 3遵义水利水电勘测设计研究院习水县铜灌口水库工程大坝优化设计报告[R].2013.9.

同被引文献5

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部