摘要
建宁县器村电站为河床式枢纽电站,已建成发电。为创造电站施工干地条件,采取了施工导流措施。本文结合工程施工实际情况对该导流方案进行简要介绍,旨在为今后遇到类似工程提供参考。
Jianning Qi Village power station belongs to riverbed hub power station,which has been constructed and put into use for power generation.Conversion diversion measures are adopted in order to create conditions for power station construction.The diversion plan is briefly introduced in the paper by using practical condition of project construction, thereby providing reference for similar projects in the future.
出处
《中国水能及电气化》
2014年第6期60-62,共3页
China Water Power & Electrification
关键词
器村电站
导流方案
导流设计
Qi Village power station
diversion plan
diversion design