摘要
风力发电建设工程近年来在新疆突飞猛进,而风电场建设过程中不可避免地给当地土壤和植被带来一定程度的破坏,人为地加剧了水土流失。文章以新疆华电达坂城风区300 MW风电工程为例,结合风电工程特点和项目区具体特点,分块分区设置防治措施,在3个区域采用水土保持工程措施、植物措施与临时措施相结合,有效地防治了项目区水土流失的发生。
The development of wind power in Xinjiang has been advanced rapidly in recent years, but the wind electric field construction process will inevitably bring the damage to the local soil and vegetation, and artificially exacerbated soil erosion. In this paper, taking the 300MW wind power project in the wind zone of Xinjiang Huadian Dabancheng as an example, combined with the specific features of the project area and characteristics of wind power projects, settings control measures by block partition. Through the combination of soil and water conservation measures, plant measures and interim measures working in the three block areas, the soil and water erosion could be controlled effectively.
出处
《林业调查规划》
2014年第3期131-135,共5页
Forest Inventory and Planning
关键词
风电场
水土流失
水土保持措施
新疆达坂城
wind electric field
soil and water erosion
soil and water conservation measures
Xinjiang Dabancheng