摘要
根据赵山渡引水枢纽工程的特点,综述了该工程的施工方案、施工工艺及施工情况,其主要内容包括:(1)分期导流方案和导流建筑物的布置;(2)采用从右岸进占单戗堤立堵截流方案进行大江截流的情况,以及一、二期围堰的填筑和防渗体的施工;(3)闸基混凝土防渗墙的施工方法、材料和机具,以及闸坝基础开挖和混凝土的浇筑;(4)发电厂房工程的设计修改、基础开挖和混凝土的浇筑等.
: According to the characteristics of the Zhaoshandu Hydrocomplex, this paper gives a summary on the construction schemes, techniques and conditions of this project, including mainly: (1) the diversion scheme by stages and layout of diversion structures;(2)closure by end dumping from right bank,filling of the first and second stage cofferdams, and construction of the diaphragms of cofferdams; (3)the construction methods, materials and machines of the concrete diaphragm in the sluice foundation, foundation excavation and concrete placing for the sluice and dam; and (4)alteration for design, foundation excavation and concrete placing for the power house.
出处
《水利水电技术》
CSCD
北大核心
2001年第2期5-8,共4页
Water Resources and Hydropower Engineering
关键词
引水枢纽工程
导流
截流
防渗墙
基础开挖
: engineering construction Zhaoshandu Water Diversion Project diversion closure diaphragm concrete placing foundation excavation