摘要 三峡永久船闸人字门顶枢预应力锚杆安装是三峡永久船闸金属结构和机电设备预埋件中难度最大的项目。工程采用的在人字门顶枢A、B拉架预留槽内预埋预应力锚杆的设计方案 ,在国内尚属首例。技术人员对安装工程的难点认真分析 ,对方案进行数次优化 ,圆满完成了任务 ,为我国人字形工作闸门顶枢预应力锚杆的安装积累了宝贵经验。 The installation of pre stressed anchorage rod of top pintle of the miter gate of Three Gorges Permanent Lock is the most difficult item in the metal structures and mechanical and electrical equipment of Three Gorges Permanent Lock. The design scheme of installing pre stressed anchorage rod in the channels of A and B tension bar in the top pintle of miter gate has been adopted, which is the first one at home. The technicians seriously analyzed the installation difficulties and optimized the scheme so that they successfully completed the project construction task. It provides valuable experience for the installation of pre stressed anchorage rod in the top pintle of miter gate in China.
作者 苏存明 王俊
出处 《水力发电》 北大核心 2001年第3期32-34,共3页 Water Power
关键词 人字门 闸门顶枢 预应力 锚杆 安装 永久船闸 三峡工程 miter gate, top pintle, pre stressed anchorage rod, installation, Three Gorges Permanent Lock
  • 相关文献

同被引文献12

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部