摘要
西柏坡发电厂300MW#1机在额定参数下带不满负荷的主要原因是汽轮机高压缸内效率低、通流面积小、汽封系统泄漏严重。大修中通过改造,使机组在额定参数下能够带满负荷运行。
Unit 1 in Xibaipo Power Plant could not operate in full load with rated parameter steam because of the low internal efficiency of the high pressure turbine,small flow path area,and serious leakage of steam gland system.All these problems are settled during overhaul.Now this unit can take full load with rated parameter steam.
出处
《河北电力技术》
1997年第3期23-27,共5页
Hebei Electric Power
关键词
高压缸
蒸汽透平
故障
汽封系统
300MW steam turbine high pressure turbine efficiency flow path area