本文介绍了安装在土耳其 AKSU(阿克苏)水电站的高速水轮发电机的设计与运行。本机选择了最佳电磁方案,对发电机的结构也进行了改型设计,克服了高速水轮发电机同类机组推力瓦温高、转子温升高、噪声大的难题。
The design and operation of high-speed hydrogenerator,installed in Turkey AKSU power station,are introduced here.The optimum electromagnetic scheme is choosed and the hydrogenerator constructions are a so reformed.All the above- mentioned measures,adopted in this generator,overcome the problems of higher temperature in thrust bearing pads,higher temperature rise in rotor winding and higher noise.
出处
《大电机技术》
北大核心
1992年第1期11-16,共6页
Large Electric Machine and Hydraulic Turbine
关键词
高速水轮发电机
水电站
设计
运行