带公共交货期窗口的提前/拖期非等同多机调度问题 被引量:3

Earliness-Tardiness Job Scheduling Problem with a Common Due Window on Non-uniform Machines
原文传递
导出
摘要 提出了公共交货期窗口下提前 /拖期惩罚的多台不同设备情形的零件排序模型 .在分析相应单机问题最优排序和最优交货期性质的基础上 ,证明该多机零件问题实际上蕴含着使系统 makespan达最小的多机零件排序问题 .由于使系统 makespan达最小的并行多机零件排序问题已被证明是 NP完全问题 ,因此提出了求解该零件排序问题的一个启发式算法 ,该算法计算复杂性低且对并行多机零件排序问题同样适用 .最后给出了两个数值例子 . A mathematical model for earliness\|tardiness job scheduling problem with a common due window on non\|uniform machines is put forward. Because the job scheduling problem contains a problem of minimum makespan, which is NP\|complete on uniform machines, a heuristic algorithm is presented to find an approximate solution for the scheduling problem after proving an important theorem. Two numerical examples illustrate that the heuristic algorithm is very effective in obtaining near\|optimal solution.
出处 《系统工程理论与实践》 EI CSCD 北大核心 2001年第4期64-69,共6页 Systems Engineering-Theory & Practice
基金 浙江省自然科学基金! ( 6980 69) 国家 863计划! ( 863 -51 1 -94 5-0 0 2)
关键词 提前/拖期 交货期窗口 零件 排序 调度问题 earliness\|tardiness JIT due window job scheduling
  • 相关文献

参考文献8

二级参考文献5

  • 1Wang D W,Comptuers Msthematics Applications,1996年,31期,95页
  • 2Wang D W,Comptuers Ind Eng,1995年,28期,425页
  • 3Hao Q,Systems Engineering-theory Methodology Applications,1994年,3期,31页
  • 4Qian S D,Operational Rescarch,1990年
  • 5Cheng T C E,Comput Opns Res,1988年,15期,91页

共引文献14

同被引文献39

  • 1张超勇,饶运清,刘向军,李培根.基于POX交叉的遗传算法求解Job-Shop调度问题[J].中国机械工程,2004,15(23):2149-2153. 被引量:108
  • 2LAUFF V, WERNER F. Scheduling with common due date, earliness and tardiness penalties for multimachine problems: a survey[J]. Mathematical and Computer Modelling, 2004,40 (5/6) :637-655.
  • 3SEN T, SULEK J M, DILEEPAN P. Static scheduling rese- arch to minimize weighted and u nweighted tardiness:a state-of-the-art survey [J], International Journal of Production Eeo nomics, 2003,83 ( 1 ): 1-12.
  • 4ESSAFI I, MATI Y, DAUZERE-PERES S. A genetic local search algorithm for minimizing total weighted tardiness in the Job-Shop scheduling problem [J]. Computers & Operations Research,2008,35(8) :2599-2616.
  • 5THIAG-ARAJAN S, RAJENDRAN C. Scheduling in dynamic assembly Job Shops to minimize the sum of weighted earliness, weighted lardiness and weighted flowtime of jobs[J]. Comput- ers& Industrial Engineering,2005,49(4):463-503.
  • 6SADEH N. Look ahead techniques for micro opportunistic Job Shop scheduling[D]. Pittsburgh, Pa. , USA:Carnegie Mellon University, 1991.
  • 7SADEH N. MICRO-BOSS:a micro-opporlunistic factory sch eduler[J]. Expert Systems with Applications, 1993,6(3) : 377- 392.
  • 8BAKER K R. Introduction to sequencing and scheduling[M]. New York, N. Y. , USA:Wisely, 1974.
  • 9OW P S, MORTON E T problem[J]. Management & The single machine early/tardy Science,1989,35(2):177-191.
  • 10CHENG T C E,GORDON V S,KOVALYOV M Y.Single machine scheduling with batch deliveries[J].European of Operational Research,1996,94(2):277-283.

引证文献3

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部