我国水电站大坝事故分析与安全对策 被引量:27

Accident Analysis of Hydropower Dams in China and Countermeasures for Safety
下载PDF
导出
摘要 对水电站大坝事故的反馈分析表明 ,大多数事故与设计阶段的失误、施工过程遗留下的隐患、运行管理中的差错等因素有关 .应强化设计、施工、运行全过程的风险意识和安全管理 .对运行中的大坝要坚持实施定期检查 ,及时维修加固和改造 ,认真进行安全注册 ,严密制定汛期和低水位时的防范措施 ,加大科研力度和开展险情预计 ,以防止重大事故的突然发生 . The feedback analysis on the accidents of hydropower dams shows that most of the accidents are related to the faults in design, the hidden perils from construction and the errors in operation management. Therefore, the risk awareness and safety management should be strengthened during the whole process of design, construction and operation. During operation, dams should be examined periodically, repaired and reinforced on time, meanwhile safety registration, the preventive measures for flood season and low reservoir levels, scientific research and emergency prediction are also necessary to prevent major accidents.
作者 邢林生
出处 《水利水电科技进展》 CSCD 2001年第2期26-32,共7页 Advances in Science and Technology of Water Resources
关键词 水电站 大坝失事 溃坝 安全 hydropower dams dam accidents dam failure dam safety
  • 相关文献

参考文献16

二级参考文献8

  • 1邢林生 方榴声.陈村拱坝侧移变形性态分析.大坝安全监测技术国际学术讨论会论文集[M].杭州,1992..
  • 2邢林生 方榴声.陈村拱坝下游面105m高程附近水平裂缝的性态分析[J].水力发电学报,1998,(4).
  • 3王志远 汤倩高.浙江里石门拱坝蓄水后的结构性态分析[J].水力发电,1987,(8).
  • 4邢林生,人民长江,1994年,7期
  • 5刘桂印,观测技术,1985年,2期
  • 6汝乃华,大坝事故与安全.拱坝,1995年
  • 7邢林生,大坝安全监测技术国际学术讨论会论文集,1992年
  • 8Xinfengjiang Dam Vibration Test Group.新丰江坝原型振动试验[J]地震工程与工程振动,1984(01).

共引文献51

同被引文献142

引证文献27

二级引证文献150

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部