摘要
通过大管径给水管线穿越河流的工程实例 ,阐述了给水管线在遇到河道冲刷、地基土液化、高覆土等不良的工程条件下的设计方案 ;根据高覆土的特殊情况 ,提出了采用复合管道结构———包封 ,详细介绍了其做法 ,并进一步介绍了钢管壁厚的计算。
By the engineering examples of which large caliber w ater supply pipelines pass through the river, the paper elaborates design scheme of water supply pipelines when it encounters bad project conditions of river ch annel erosion, foundation soil liquidation, high earthing and so on. According t o special situation of high earthing, the paper puts forward using compound pipe structure--pack, introduces in detail its method, and then introduces calcu lation of steel pipe wall thickness, treatment methods of foundation soil liquid ation, treatment methods of resistant to erosion.
出处
《山西建筑》
2001年第2期123-123,152,共2页
Shanxi Architecture
关键词
大管径穿越汾河
抗冲刷
地基土液化
给水管线
水源
黄河
large caliber, analysis of resistant to erosi on, treatment of foundation soil liquidation, concrete pack