石泉水电站消力戽运行情况 被引量:2

The Dissipation Bucket of Shiquan Waterpower Station
下载PDF
导出
摘要 文中简述了石泉水电站及消力戽运行情况 ,观察到随着下泄流量的减小 ,消力戽从戽流形态向不稳定的挑戽过渡形态 ,又随着向挑流形态变化。提出在挑戽流转化时 ,要缓慢开启闸门 ,并规定了各孔的启闭程序以减少下游冲刷。文中还介绍了消力戽的检修及改造 ,提出了防止蚀损及蚀损补修措施。 The paper is a brcef description of Shiquan Power Station and the operation of the dissipation bucket observed in the site.Discharged water from the spillway changes from the bucket regine into an unstable jet flow with the decreasing of flow.A suggestion is proposed that during the transition stage opening of the gate should be slow,an order of opening and closing the gates on the spillway is set for reducing the scouring of the dawnstream river bed.The paper gives an illustration of examination and repair of the bucket and measures for protection against erosion.
作者 郭锡春
出处 《水力发电学报》 EI CSCD 北大核心 2001年第2期106-112,共7页 Journal of Hydroelectric Engineering
关键词 消能 消力戽方式 蚀损 补修 石泉水电站 Energy dissipation Buckct drssipator Erosion Repair
  • 相关文献

参考文献6

  • 1陈益琨 何Jing.石泉水电站技术设计报告[M].,1978..
  • 2于绍奉 宋津钟.消力戽改造水工模型试验报告[M].,1985,3..
  • 3李连玉 崔增华 等.石泉水电站大坝运行综合总结报告[M].,1989,9..
  • 4李连玉,石泉水电站大坝运行综合总结报告,1989年
  • 5于绍奉,消力戽改造水工模型试验报告,1985年
  • 6陈益琨,石泉水电站技术设计报告,1978年

同被引文献13

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部