摘要
根据隔河岩大坝外观变形GPS自动化监测系统的大量观测资料(1998年6月-1999年12月),全面分析并评价了间距为1km的两个工作基点相对定位的三维精度。结果表明,2小时解的精度为∧±2.86mm(n)、±2.50mm(E)和±6.52mm(U);6小时解的精度为±2.06mm(N)、±1.77mm(E)和±4.49mm(U);垂直方向的精度约水平方向的2.5倍。这一精度分析结果具有大子样容量的特性.客观反映了GPS在单一短基线进行相对定位的三维精度情况,可为GPS用于精密工程测量和变形监测的方案设计提供参考。
On the basis of a vast amount of GPS data (from June 1998 to December 1999) collected from GPS automatic monitoring system of outside deformation for Geheyan Dam, in this paper the 3- dimentional relative positioning precision for tow working datum marks about lkm long of this system was analyzed and evaluated. Results showed that the precision of 2h solutions was ±2.86 mm(NS direc- tion) ±2.50 mm(EW direction) and ±6.52 mm(U direction), that of 6h solutions was ±2.06 mm(NS direction)±1.77 mm(EW direction) and ±4.49 mm(U direction), and the precision in vertical compo- nent was about 2.5 times greater than in horizontal directions. The statistic analysis results had the char- acteristic oflarge Sample quantity, reflected veriy the 3-dimentional relative positioning precision for a single short baseline, and provided reference data for the design of GPS used for precise engineering sur- veying and deformation monitoring.
出处
《测绘工程》
CSCD
2001年第2期41-44,共4页
Engineering of Surveying and Mapping
基金
测绘遥感信息工程国家重点实验室资助项目(990201)。