摘要 元宝山电厂2号炉自投运以来,一直不能带满负荷运行,东北电力试验研究院分析了锅炉特性,进行了分级送风、低氧燃烧的试验研究工作。文中分析了欠氧燃烧原理及运行特性,并对其正、负两方面的影响进行了探讨。经技术改造,该机组运行负荷已达600MW,锅炉实现了满负荷连续稳定运行。 No.2 boiler in Yuanbaoshan Power Plant could not operate at full load ever since it went into operation.Northeast Power Testing and Research Institute analyzed the boiler characteristics,conducted testing and research works on stage forced draft,low oxygen combustion,analyzed the principle of under oxidized combustion and operation characteristics,and explored its both positive and negative impacts.Through retrofitting,No.2 generating unit has been able to operate up to 600 MW,realizing full load continuous stable operation.
作者 张永兴
出处 《中国电力》 CSCD 北大核心 1998年第9期3-7,共5页 Electric Power
关键词 电厂 600MW机组 锅炉 分级燃烧 试验 boiler stage combustion slagging cha ra cteristics combustion adjustment
  • 相关文献

同被引文献35

引证文献5

二级引证文献63

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部