摘要
水布垭工程挖填工程量巨大 ,土石方调配问题意义显著 .通过对该问题的分析 ,总结了料物调配的规律 ,提出了此问题的数学模型 ,据此即可编制程序 ,实现调配活动计算机化 .同时列出了计算机调配汇总结果 ,并与设计结果作了对比 ,体现了其技术经济价值 .本问题的解决办法亦可供解决其他料物调配问题时使用 .
The problem of allocation of earth_rock volumes has obvious significance due to its huge amount for the Shuibuya Project. Through analyzing the problem, a mathematical model for this problem is established, and on this basis the corresponding software is programmed so as to realize computerization for the problem. Finally, the results of allocation by computer are collected and listed, and compared with the design results. It shows that the allocation by computer has technical and economic values. The solving method of this problem can also be used for the allocation problem of other materials.