介绍了 1997年以来湖北电网AGC工作的状况以及开展AGC工作采取的措施 ,分析了湖北电网省间交换功率、峰谷差和装机容量给湖北电网的AGC控制带来的影响。针对湖北电网AGC网供计划所面临的问题 ,提出了解决问题的方案。
The work condition of automatic generation control(AGC) in Hubei Electric Network since 1997 was introduced.The influence from power interchange between provinces,difference between peak to valley and capacity of generator in Hubei electric network,on the AGC control was analyzed.The paper put forward some methods to solve the power interchange plan for the AGC control.
出处
《湖北电力》
2001年第2期56-57,共2页
Hubei Electric Power