摘要
立井井筒采用国内目前最先进的施工技术和混合作业施工法 ,采用立井机械化配套 ,即采用大绞车、大吊桶提升出矸 ,大抓岩机抓岩 ,大段高 (3 0m)整体下行刃脚金属液压模板砌壁 ,6臂伞钻打眼。光面、光底、弱震、弱冲深孔光爆技术 ;改善作业方式 ,实行“混合滚班制”作业和“千分制”计件承包 ,提高正规循环率 ;实行工作面预注浆和壁后注浆 ,有效控制井筒涌水 ;实施项目法管理 。
Advanced working technique and mixed operation method is adopted in vertical shaft collar,mechanized sets of vertical shaft:big winch,big well-bucket hoist waste rock,big grab lnoader grab rock,largh section high (3.0 m) whole down,knife of metal hydraulic plate cut wall,drilling machine with six arm umbel drillshole.Plain face and bottom,weak shock,light blasting in deep nole technique,working way is tmpnved 'mixed roll work in shifts' working and 'thousand fen' piece constraction is practised,pre-injection and injection beside wall is practised in workface,water bursting of shaft collar is controlled;manayement of item method is implemented,and quick working is realized.
出处
《煤》
2001年第4期1-2,6,共3页
Coal