在工程建设中 ,总图专业进行选址至关重要。而选址工作极为复杂、纷繁 ,涉及面广 ,需要考虑的问题很多。通过对滇池草海底泥疏浚工程中的底泥堆场进行选址 ,指出总图专业设计人员 ,必须开展深入、细致的调查研究 ,做好方案优化工作 ,才能造福于人类 ,获取较好的社会、经济。
In project construction,the selection of plant site by General Layout Department is quite important,and the procedures of plant site selection are very complicated,involving a wide variety of issues needed to be considered.In the selection of substrate-sludge stacking yard of Caohai substrate sludge dredging work in Dian Lake,the designers from General Layout Department had thoroughly and carefully investigated the situations,optimized the design schemes (options),and finally achieved excellent social,eeconomical and environmental benefits.
出处
《有色金属设计》
2001年第2期48-51,70,共5页
Nonferrous Metals Design
关键词
总图专业
方案优化
工程建设
厂址选择
General Layout Department (profession)
reasonable plant-site selection
scheme (option) optimization