CANDU 6核电站反应堆物理启动

CANDU 6 Nuclear Power Plant Reactor Physical Startup
下载PDF
导出
摘要 CANDU6堆调试期间的物理启动和物理调试试验主要在B阶段和C阶段进行,同时也包括A阶段的堆芯装料后的临界监督。基于韩国月城4号机组的物理调试,介绍了物理调试试验数据的预模拟分析、试验方法以及试验结果的分析和评估,并指出了试验中的重要注意事项。 Physical startup and physical commissioning test of CANDU 6 during commissioning are primarily performed at Phases B and C, and critical monitoring after fuel loading at PHASE A is also included. Based on physical commissioning of Wolsong Unit 4 of Korea, the pre-modeling analysis, test method as well as analysis & evaluation of the test results of the physical commissioning test data, indicating the points for attention during testing are presented.
作者 陈明军
出处 《核科学与工程》 CSCD 北大核心 2001年第2期166-175,共10页 Nuclear Science and Engineering
关键词 CANDU6堆 物理启动 物理调试试验 PHASE-B PHASE-C 物理模拟分析 反应堆 重水堆核电站 CANDU 6 reactor Physical startup Physical commissioning test PHASE-B PHASE-C Physical modeling analysis
  • 相关文献

参考文献4

  • 1Rouben B.Reactor Fuelling Simulation Program-RFSP: Program Description[].COG-- AECL.1995
  • 2AECL/KAERI.Phase-B Physics Simulation Report[]..1995
  • 3.Commissioning Procedure CP2, CP3, 86-00363 (00364 )-CP2, CP3[]..1995
  • 4.Commissioning Procedure CP4, W3 (4)- MD01-00363 (00364)-CP4[]..1995

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部