摘要
赛歧港下白石码头投产后发现护岸倒滤层严重漏砂,由于翻修倒滤层会危及护岸的安全,而采用注浆法加固,经过现场反复试验,不断调整浆液的配合比和施工工艺,最后达到预期的目的。
Serious sand loss occured at the filter layer of revetment for Xiabaishi Wharf of Saiqi Port aller Putting into operation. Since it will endanger the revetment by reconstructing filter layer, mortar jetting method is adopted for consolidation. Through repeated site test and by regulating the miking ratio of mortar, it achieved desired resultsat last.
出处
《水运工程》
北大核心
1999年第6期34-36,共3页
Port & Waterway Engineering