摘要
针对土石方施工机械在联合作业过程中 ,型号不同的多台辅助施工机械与主导施工机械在配合施工中 ,完成单次土方作业循环时间参差不齐的情况 ,利用排序法建立了非同型号辅助施工机械完成单次土方作业循环时间控制模型。并用实例进行验算 ,获得了不同型号辅助施工机械与主导施工机械配合施工的最佳序列和循环时间。
In the light of earthwork mechanisation in associtate operation, when the many aid mechanisations are different, and the circle time of them finishing one time earthwork is not equal,we adopt the method about queue, build the model of circle time control about the different type aid mechanisation finishing one time earthwork work.And it is used to make a series of calculation by living example, obtains the optimal queue and circle time about the different type aid mechanisation with the major mechanisation associtated with construction. It's a kind of useful method about mechanisation construction.