摘要
介绍了采用控制爆破技术拆除湖南株洲电厂发电车间旧厂房的工程实例。文中讨论了钻爆参数设计、预处理、爆破网路以及安全措施 。
An engineering example to demolish an old industrial building of electric power workshop in Zhuzhou Power Plant by the controlled blasting technology was introduced The drilling and blasting parameter design,the pretreatment,blasting circuit,safety precautions and others were discussed In particular,the delay blasting technology was expounded in more detail
出处
《工程爆破》
2001年第3期34-38,共5页
Engineering Blasting
关键词
厂房
爆破拆除
控制爆破
发电厂
爆破设计
Industrial building
Demolition blasting
Controlled blasting