济钢5^#高炉冷却壁破损分析 被引量:3

The Breakage Analyses on Cooling Wall of No.5 Blast Furnace of Jigang
下载PDF
导出
摘要 根据济钢第一炼铁厂 5 #高炉在 2 0 0 0年大修中的破损情况 ,分析筋条镶砖式冷却壁纵裂原因是冷却壁热面温度不稳定 ,而全覆盖式冷却壁由于其结构能使冷却壁本体温度变化幅度小 ,且有很强的抵抗裂纹扩展的能力 ,因而破损速度较慢。为了有效保护冷却壁 ,应使冷却壁热面能够挂结渣皮 ;同时应注意全覆盖式冷却壁的使用和冷却壁的结构设计及软水流量、软水脱汽等问题。 According to failure analyses of the cooling wall of No.5 blast furnace in No.1Iron Making Plant of Jigang in heavy repair in 2000, the main cause of longitudinal crack of cooling wall with ribs enchased in bricks is the temperature instability of hot side of cooling wall. But the full coverage cooling wall can keep structure itself little changing of temperature and have stronger capability to resist the extending of crack, so it can slow down the breakage rate. To protect the cooling wall in effect, the best way is to enable hot side of cooling wall to cling some slag. At the same time ,the service and structure design of full coverage cooling wall and the probolems of flux and degas of soft water should be paid more attention to.
机构地区 济南济钢设计院
出处 《山东冶金》 CAS 2001年第4期6-8,共3页 Shandong Metallurgy
关键词 高炉 冷却壁 全覆盖式冷却壁 纵裂 热面温度 炼铁 blast furnace cooling wall full coverage cooling wall longitudinal crack hot side temperature
  • 相关文献

参考文献2

共引文献3

同被引文献20

引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部