摘要
从负荷计算、电网规划、导线截面选择和自备发电站组建等方面对施工临时供用电方案进行理论分析 ,并给出拟定该方案的步骤、方法及实例。
From a lot of aspects such as load computation, electrified wire netting plan, wire section choice and self-equipped power plant construction, this paper has a theoretical analysis on temporary supplying and consuming electricity scheme during construction, and give out steps, methods and examples on applying such scheme.
出处
《太原科技》
2001年第3期18-19,共2页
Taiyuan Science and Technology
关键词
施工
临时供用电
方案拟定
铁路施工
construction, temporary supplying and consuming electricity, scheme