摘要
铜鼓滩水利枢纽工程曾规划为大藤峡水电站的反调节水库 ,1983年提出要先兴建铜鼓滩工程 ,且出版了初步设计报告书。其中对推移质泥沙做了大量工作。广西有关推移质观测的资料较少 ,文章介绍了坑测与器测推移质方法 ,计算推移质基本输沙率 ,断面输沙率乃至年输沙量等方法。
The Tonggutan key WR project was ever planned as the equalized reservoir of the Datengxia hydropower station. Its primary design report had been printed and the engineers made a great quantity of works for silt bed load. The pit testing and tool testing methods of bed load: the methods of computing bed load basic sediment ratio, section sediment ratio and year's sediment discharge,etc. are introduced here for reference.
出处
《广西水利水电》
2001年第3期8-12,共5页
Guangxi Water Resources & Hydropower Engineering