摘要
土石坝施工的核心是土石料的填筑压实 ,压实质量的好坏 ,关键在于能否正确执行压实标准。本文基于某些工程在执行压实标准中存在一些问题 ,对此作了简略的分析 ,以引起注意外 ,着重对压实标准的定义、条件、相互关系作了较全面的阐述 ,其目的旨在正确的应用压实标准 。
The key link of embankment dam construction is fil ling and compacting of earth and rock materials and the compaction quality d epends on whether the compacting standard is properly executed. A brief analysis is made on the problems in execution of the compacting standard. A comprehensiv e description is given to the definition, conditions and interrelation of compac ting standard for the purpose of correctly applying the compacting standard and ensuring construction quality.
出处
《西北水电》
2001年第3期33-37,共5页
Northwest Hydropower
关键词
土石坝
土石料
压实标准
压实度
相对压实度
embankment dam
earth and rock materials
compact ing standard
compactness
relative compactness