摘要
结合广东沙角发电总厂在进行 A2机组 (2 0 0 MW)的控制系统更新改造中 ,将电气控制纳入 DCS系统的成功经验 ,对大型火力发电机组实现一体化控制的有关问题 ,特别是电气控制方面的技术问题进行了研究和探讨。
In connection with the successful experience of inodification from mtegrerted electric control system into distributed control system (DCS) in No.A2 generator set(200 MW)Shajiao Power Plant Guanding,the problems of the control system merged into an organic whole for large thermal power gennator set,especially related to electric control were discussed.
出处
《湖北电力》
2001年第5期21-22,共2页
Hubei Electric Power