摘要
10MW高温气冷实验堆共有10套控制棒组件及其驱动机构,用于高温堆启动、功率运行和停闭过程中补偿和调节所需的反应性变化,并保证足够的停堆裕度。为确保达到工程设计的要求,对全部控制棒组件及驱动机构,都在实验室进行了热态试验,在高温堆上进行了安装后调试、以及首次临界前的测试。各项数据表明,所有驱动机构运行良好,控制棒的提棒、落棒运行功能正常,位置保持功能正常,棒位显示准确。
There are 10 sets of control rods and driving devices in 10 MW High Temperature Gas-cooled Test Reactor (HTR-10). The control rod system is the controlling and shutdown system of HTR-10, which is designed for reactor criticality, operation, and shutdown. In order to guarantee technical feasibility, a series of verification tests were performed, including room temperature test, thermal test, test after control rod system installed in HTR-10, and test of control rod system before HTR-10 first criticality. All the tests data showed that driving devices working well, control rods running smoothly up and down, random position settling well, and exactly position indicating.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2002年第1期41-44,共4页
Nuclear Power Engineering
基金
国家"863"计划能源重点项目