摘要
描述了某软土地基上大型填土工程在施工过程中发生的滑坡现象 ,根据室内试验和现场勘测结果 ,进行了滑坡前和滑坡后的稳定计算 ,探讨了滑坡的原因 ,提出了整治措施 ,介绍了治理效果。不仅为软土地基填土工程的设计和施工提供了有益的资料 。
The landslide of a large scale filled project on soft clay occurring during construction is described in this paper. Based on laboratory test and field data, the slope stability before and after the landslide is calculated, and the cause responsible for the landslide is analyzed. Finally a method for landslide correction is proposed, and the correction results are also given. All these provide useful data for design and construction of filled projects on soft clay, and can be used for reference of the other landslide correction.
出处
《岩土工程学报》
EI
CAS
CSCD
北大核心
2002年第2期198-201,共4页
Chinese Journal of Geotechnical Engineering
关键词
填土工程
土坡稳定
滑坡
治理
filled project
slope stability
landslide
correction