摘要
以高层建筑混凝土结构施工过程中的施工活荷载为研究对象 ,根据现场调查结果 ,通过统计分析 ,提出了施工过程各阶段施工活荷载的数学模型 ,按 95 %的保证率给出了不同施工活荷载的数值。可供结构设计人员作施工阶段安全性验算时参考。
Miao Jijun Gu Xianglin Fang XiaomingThe construction live loads of high rise reinforced concrete buildings were selected as the research objectives. Based on the results of the survey on the work site,the mathematics models of live loads in different stages of construction process for high rise reinforced concrete buildings were proposed through statistic analysis. The standard values of construction live loads are brought forward at last for the purpose of safety calculation in the construction process.
出处
《建筑结构》
CSCD
北大核心
2002年第3期7-9,共3页
Building Structure
基金
上海市高等学校青年科学基金资助项目
关键词
高层建筑
混凝土结构
施工
活荷载
统计分析
high rise reinforced concrete building
construction live load
statistic analysis