摘要
在高层建筑转换层的整体现浇混凝土施工中 ,多用扣件式钢管脚手架组合成三维方格支撑系统 ,本文依据在深圳捷佳大厦转换层现浇混凝土施工中布置的变形观测资料 ,对这种支撑系统进行了承载力分析 ,验证了计算立杆、横杆间距公式的适用性。
In integer on\|site pouring concrete construction of transition layers of high\|rise buildings, normal scaffolding steel pipes generally are combined together to form a three dimensions grids support system. According to deformation measure materials of this kind support system in the on\|site pouring concrete construction of the transition layer of Shenzhen Jiejia Mansion, authors analyze bearing capacity of this kind support system, and validate the applicability of the calculation formulas of spaces among standing and cross bars.
出处
《施工技术》
CAS
北大核心
2002年第3期15-16,共2页
Construction Technology
关键词
高层建筑
转换层
支撑系统
支撑
承载力
变形
high\|rise building
transition layer
support system
bearing capacity
deformation