棉花滩水电站碾压混凝土大坝施工 被引量:2

Construction of RCC dam of Mianhuatan Hydropower Station
下载PDF
导出
摘要 棉花滩水电站大坝工程自 1998年 4月动工 ,至 2 0 0 1年 4月完工 ,历时 3年 ,在国内水电工程建设中处于领先地位。大坝工程的全干法人工砂石料生产系统为国内首创并取得成功 ,碾压混凝土全面应用斜层平推碾压施工工艺 ,创造性地采用拌和楼拌制变态混凝土 ,大坝下游斜坡面采用四层翻升模板 ,这些施工工艺的采用 ,为大坝工程建设保证了工期、质量 。 The dam project of the Mianhuatan Hydropower Station was started in April 1998 and completed in April 2001. The completion of such scale dam within 3 years ranks the leading position in the construction of hydropower projects in China. The full dry artificial aggregate production system of the dam project ranks the first in China and has gained success. The construction of RCC adopted inclined layer push roller compaction technique and creatively used the batch plant to mix the metamorphic concrete. The construction of the downstream slope surface of the dam adopted 4 layer turn over form technique. The application of these techniques guarantees the progress and quality of the dam construction and increases the economic benefit.
出处 《水力发电》 北大核心 2001年第7期41-44,共4页 Water Power
关键词 碾压混凝土坝 砂石料系统 碾压混凝土施工 施工管理 棉花滩水电站 斜层平堆 拌和楼拌制 四层翻升 模板 dam, aggregate system, RCC construction, construction and management, Mianhuatan Hydropower Station
  • 相关文献

同被引文献4

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部