摘要
总结李家峡水电站发电初期的经验教训 ,在此基础上 ,对公伯峡水电站 2 0 0 4年底两台机组同时发电的可行性做了初步分析。其结果表明 ,只要合理组织 ,严格管理 ,并确保 2 0 0 1年 6月份厂房开始浇筑混凝土 ,这个计划是能够实现的。
By drawing on the experience and lessons at the initial generation stage of the Lijiaxia power station, preliminary analysis is conducted on feasibility of two units of the Gongboxia power station commissioned by the end of 2004. The results indicate this schedule can be realized provided that the construction is well organized and strictly controlled and it is ensured to start concreting the powerhouse in June of 2001.