摘要
河南七里岗水泥厂是由天津水泥院承担设计与调试的第三条700t/d新型干法生产线。该院与厂方密切合作,仅用7个多月时间,解决了生产中出现的技术问题,完成了调试任务,达到了各项考核指标。1990年9月12日~15日连续三天试生产出2182t水泥熟料,平均日产727t,达到并超过了700t/d的设计指标。本文介绍了调试中的主要问题及达标过程,是700t/d生产线调试工作的又一次经验总结。
QiLigang Cement Plant,Henan Province,is the third new dry process line of700t/ d designed and commissioned by TCDRI.Cooperating with the engineers,TCDRI has spent only 7 months to complete the commissioning by tackling many problems and reaching all design targets.With 3 days contineous operation from Sept. 12,to Sept. 15 in 1990,the total production of clinker was 2182t,i.e.,the average daily clinker throughput was 727t which exceeds the rated capacity 700t/ d.A detailed description is given in the article on the main problems solved and experiences obtained during commissioning.
出处
《水泥技术》
1991年第4期3-7,共5页
Cement Technology