摘要
本文叙述青岛前湾港区利用大桥岛的沧口水道的砂源,用自航耙和绞吸式两种不同类型的挖泥船接力施工,改陆上回填为水上无围堰吹填砂施工和工程质量控制等措施。通过两年的工程实践取得成功,并获得了明显的社会和经济效益。
This paper makes description on the new construction method of reclama-tion work for Qianwan Port Area of Qingdao Harbour, in which the reclaiming was carriedout without building coffer-dams.By use of the sand material exca vated from Da qiao Island and Cangkou Waterway, two dredgers, one self-pro pelled trai ling suction hopper type and one cutter head type, were arranged to pump the sand dircctly into position, working by relays. The whole work was successfully completed within two years, and achieved prominent social and economical benefits.