摘要
针对全面回采河南某小型地下金矿遗留"П型矿柱"和协同处理空区的需要,对空区处理和矿柱回采的技术原则和制约因素进行了研究,提出了胶结充填空区后多类炮孔组合爆破回采"П型矿柱"的方法,在典型区域开展现场工业试验,区域内实现了充填处理空区和回采间柱的双重目的,最终获得了87%的矿柱回采率和95%空区处理率的良好效果。
According to the need of comprehensive recovery of П-shape pillars and the coordinated treatment of goaf in a small underground gold mine in Henan province,the technical principles and restrictive factors for goaf treatment and pillar recovery were studied.And the method of combined blasting in multi-type blasting holes after cemented filling of goaf was put forward forП-shape pillar recovery.Field work was carried out in typical areas,and the results showed that the dual purposes of filling the goaf and recovering the pillars were realized,and good results were achieved with pillar recovery of 87%and goaf treatment rate of 95%.
作者
辛向东
陈江川
李伟明
XIN Xiangdong;CHEN Jiangchuan;LI Weiming(China Gold Group Zhongyuan Mining Co.,Ltd,Sanmenxia,Henan 472200,China;Changsha Institute of Mining Research Co.,Ltd,Changsha,Hunan 410012,China)
出处
《矿业研究与开发》
CAS
北大核心
2018年第11期6-8,共3页
Mining Research and Development
关键词
П型矿柱
矿柱回采
组合爆破
胶结充填
П-shape pillar
Pillar recovery
Combined blasting
Cemented filling