摘要 为解决大型无粘结沉降钢筋混凝土箱涵的可行性研究,高速公路项目一个10孔8╳3m的箱涵为依托,采用midas Civild梁格法建模进行分析,分析钢筋混凝土箱涵沉降缝设置的必要性和适用条件。结果表明,只要箱涵的强度满足要求,可以减少或减少沉降缝,为大型钢筋混凝土箱涵的设计和施工提供了理论依据和参考。 Aimed at figuring out the feasibility study on large-scale reinforced concrete box culvert without settlement joint, take a highway project in Angola as the research object, based on which a Midas Civil model was built for overall study.The results show that as long as the strength of the box culvert meets the requirements, the settlement joint can be omitted or less set.The findings provide theoretical basis and reference for the design and build of large-scale reinforced concrete box culvert.
作者 陈华良 Chen Hualiang
出处 《中国建材科技》 2018年第6期42-43,共2页 China Building Materials Science & Technology
关键词 钢筋混凝土 箱涵 沉降缝 reinforced concrete box culvert settlement joint
  • 相关文献

参考文献3

二级参考文献4

  • 1奚绍中 郑世瀛.应用弹性力学[M].北京:中国铁道出版社,1985.147-151.
  • 2中交公路规划设计院.JTJD62--2000公路钢筋混凝土及预应力混凝土桥涵设计规范[S].北京:人民交通出版社.2012.
  • 3交通运输部公路科学研究院JTGF80/1-2012公路工程质量检验评定标准[S].北京:人民交通出版社,2012.
  • 4周一勤,金云雷.非均匀沉降连续箱涵的受力分析[J].浙江交通科技,2000(2):1-4. 被引量:1

共引文献14

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部